The Greece-Bulgaria interconnector may see its capacity boosted from the current 3 bcm/y to a total 5 bcm/y as early as 2025. With the incremental capacity process currently ongoing, ICGB is scheduling the next steps in coordination with adjacent transmission system operators. “With the non-binding phase of the process completed, we received indications for significant market interest in expanding the pipeline’s capacity. The binding phase will come in July 2024 – when energy traders and shippers commit to booking capacity”, said ICGB’s Executive Officers George Satlas and Teodora Georgieva during a meeting of the TSOs under the Vertical Gas Corridor (Greece, Bulgaria, Romania, Hungary).