ICGB’s management met with Bulgarian regional minister arch. Shishkov and representatives of the construction company AVAX regarding the finishing works on the IGB pipeline

The finishing works on the gas interconnector Greece - Bulgaria is in the process of implementation and ICGB expects them to be realized within the timeline declared by the EPC contractor and in accordance with all the requirements of the technical project.

The Greek construction company AVAX is responsible for the implementation of three main activities, divided into separate stages after approval by the Bulgarian Ministry of Regional Development and Public Works. They are not directly related to the commercial operation of the gas pipeline but still remain part of the EPC contract signed with the independent transmission operator ICGB and need to be performed in accordance with the requirements of the contracting authority and the approved technical design.

During a meeting between the management of ICGB, the construction contractor, the leadership of the Bulgarian Ministry of Regional Development and Public Works, representatives of the construction supervision, and the project’s designer, it was noted that the main activities are in three directions - completion of a spare optical cable with the placement of the required markers and backfilling of shafts, construction of a part of an access road to the gas metering station near Stara Zagora and implementation of anti-erosion measures along the route of the interconnector.

"For us, it is extremely important that these stages are completed by the contractor qualitatively and according to the requirements in the documentation. We appreciate the readiness of the Ministry for assistance in carrying out the remaining finishing activities in an optimal timeline and in a manner that fully complies with Bulgarian legislation. The dialogue continues and next week we will have a follow-up meeting, after which we expect to hear concrete decisions and deadlines from the contractor", said ICGB Executive Officers Teodora Georgieva and George Satlas after the meeting.

According to them, completing the spare optical cable is at an advanced stage and is expected to be finalized and documented in January. ICGB’s management also emphasized on the importance of finalizing the anti-erosion measures along the route as soon as possible, so that in case of a mild winter the works would not stop and allow for quicker completion. At a subsequent meeting with the Ministry’s team next week, it will be discussed how exactly this should be implemented so that the approach fully complies with the local legislation and is applicable and effective given the specific conditions in Bulgaria.

Έργο IGB

Ο Διασυνδετήριος Αγωγός Φυσικού Αερίου Ελλάδας-Βουλγαρίας συγχρηματοδοτείται από το Ταμείο Ανάκαμψης του
Προγράμματος Ενέργειας της Ευρωπαικής Ένωσης.

Η αποκλειστική ευθύνη αυτής της δημοσίευσης ανήκει στον συγγραφέα.
Η Ευρωπαϊκή Ένωση δεν ευθύνεται για οποιαδήποτε χρήση των πληροφοριών που εμπεριέχονται σε αυτήν.

Co-financed by the Europen Union, Europen Energy Programme for Recovery  European Regional Development Fund Operational Program Innovation and Competitiveness

Cookies

Χρησιμοποιούμε cookies για να διασφαλίσουμε ότι ο ιστότοπος λειτουργεί σωστά. Επιλέγοντας την επιλογή "Αποδοχή", συμφωνείτε με τη χρήση όλων των cookies σύμφωνα με τις πληροφορίες για τη χρήση των cookies στον ιστότοπο.

Αυτά τα cookies έχουν ρυθμιστεί να εμφανίζουν τον πίνακα ειδοποιήσεων κατά την πρώτη φόρτωση του ιστότοπου, αφού το αποδεχτείτε, το μήνυμα θα είναι κρυφό για τις επόμενες 365 ημέρες.

Αυτά τα cookies χρησιμοποιούνται για την παρακολούθηση της χρήσης και της απόδοσης της εφαρμογής. Παρακολουθούν ανώνυμα αναγνωριστικά με σκοπό τη συλλογή δεδομένων, βοηθώντας μας να διασφαλίσουμε την αποτελεσματική λειτουργία και να επιλύσουμε τυχόν προβλήματα απόδοσης. Δεν περιέχει προσωπικά στοιχεία και όλα τα αποθηκευμένα δεδομένα είναι ανώνυμα. Το cookie παρακολουθεί επίσης περιόδους σύνδεσης που περιλαμβάνουν συγκεκριμένες σελίδες και λειτουργίες, χρησιμοποιώντας μια μοναδική τιμή για την περίοδο λειτουργίας του προγράμματος περιήγησης με σκοπό την καλύτερη παρακολούθηση της απόδοσης.