Μετάβαση στο κύριο περιεχόμενο

As of mid-April, 91% of all construction activities for the IGB pipeline have been completed

The remaining works are the two gas metering stations near Stara Zagora and Komotini. Both are progressing well - GMS Stara Zagora is completed at 87% and the pneumatic testing of the station is expected to begin around end of April. The gas metering station in Komotini - a significantly larger facility, is ready at the level of 66% and the EPC contractor has committed to complete it by the end of June at the latest.

The dispatching center near the Bulgarian city of Haskovo is almost finished. With 97% of the construction work already done, installing and testing the instrumentation and control systems is the next planned step.

Reinstatement has already started along the entire route of the pipeline. All 182-kilometers of the interconnector should be restored in their original condition in accordance with all applicable environmental standards and local legislation. As of mid-April, more than 70 km have already been fully reinstated.

Έργο IGB

Ο Διασυνδετήριος Αγωγός Φυσικού Αερίου Ελλάδας-Βουλγαρίας συγχρηματοδοτείται από το Ταμείο Ανάκαμψης του
Προγράμματος Ενέργειας της Ευρωπαικής Ένωσης.

Η αποκλειστική ευθύνη αυτής της δημοσίευσης ανήκει στον συγγραφέα.
Η Ευρωπαϊκή Ένωση δεν ευθύνεται για οποιαδήποτε χρήση των πληροφοριών που εμπεριέχονται σε αυτήν.

Co-financed by the Europen Union, Europen Energy Programme for Recovery  European Regional Development Fund Operational Program Innovation and Competitiveness

Cookies

We use cookies to ensure that the website functions properly. By selecting the "Accept" option, you agree to the use of all cookies in accordance with the Information for the use of cookies on the site.