Μετάβαση στο κύριο περιεχόμενο

The IGB gas pipeline with Act 15 for the territory of Bulgaria

The Greece-Bulgaria interconnector now has Act 15 for the territory of Bulgaria. The pipeline commissioning procedures progress on schedule and commercial operations will begin on October 1st.

Act 15 certifies that the facility is completed and technically sound, as the EPC contractor - the Greek company AVAX, hands it over as a completed site to the contracting entity - the independent gas transmission operator ICGB AD. "This is the last step we have to take towards obtaining Act 16 in Bulgaria and the corresponding Permit for Use. We have provided the institutions with all the necessary documents, and we expect the administrative procedures to be completed by the end of next week, so that we can start commercial operation on October 1st as planned," said ICGB Executive Officers Teodora Georgieva and George Satlas.

In order to optimize the process of putting the pipeline into operation and issuing a Use Permit, ICGB sent in advance requests for preliminary opinions and/or necessary documents to 27 controlling authorities, municipal administrations, operating companies and others. As a result, to date, positive positions have been received from all relevant parties. In order to further reduce the administrative deadlines, all the necessary documentation has been previously submitted to the Bulgarian Directorate for National Construction Control (DNCC) and has already been reviewed. "We are awaiting the convening of a committee for Act 16, we have taken all the necessary steps for that to be possible," the ICGB Executive Officers said.

Georgieva and Satlas emphasized that in parallel, work continues for the necessary operational permit in Greece, so that before the end of September the facility will be licensed on Greek territory as well. The 72-hour tests, during which natural gas is transported at working pressure in the direction from Komotini to Stara Zagora, have already been performed. "There are no technical issues or setbacks, everything is ready for commercial operation," the two announced.

Given the importance of timely commissioning of the IGB pipeline and the start of the heating season, the remaining activities as part of the project are divided into phases, with today's signing of Act 15 between ICGB, the construction company, the construction and author's supervision marking the end of the first phase of these activities. This phase contains all the elements that are of direct importance for the start of commercial operation of the gas pipeline. Secondary activities are identified in a separate stage that needs to be completed by the Greek company AVAX as part of their contractual obligations. All secondary activities identified under the additional phase no not directly affect the operational readiness of the facility - e.g., asphalt laying, anti-erosion measures, spare optical cable. Work on all above-mentioned activities continues, and their final implementation will be inspected by both the contracting entity and the relevant institutions and will be the subject of a separate Act.

IGB is of key importance for increasing the security of gas supplies and for ensuring the diversification of natural gas sources for Bulgaria and the wider region of Southeast Europe. The project connects Bulgaria to the Southern Gas Corridor and will enable secure supplies from a variety of sources to countries in Southeast and Central Europe, including Moldova and Ukraine.


For more information:
Diana Zaykova
Action Global Communications Bulgaria
diana.z@actionprgroup.com
+359 885 074 422
+359 885 614 131

Rossitza Donkova
rossitza.d@actionprgroup.com
+359 888 343 661

Έργο IGB

Ο Διασυνδετήριος Αγωγός Φυσικού Αερίου Ελλάδας-Βουλγαρίας συγχρηματοδοτείται από το Ταμείο Ανάκαμψης του
Προγράμματος Ενέργειας της Ευρωπαικής Ένωσης.

Η αποκλειστική ευθύνη αυτής της δημοσίευσης ανήκει στον συγγραφέα.
Η Ευρωπαϊκή Ένωση δεν ευθύνεται για οποιαδήποτε χρήση των πληροφοριών που εμπεριέχονται σε αυτήν.

Co-financed by the Europen Union, Europen Energy Programme for Recovery  European Regional Development Fund Operational Program Innovation and Competitiveness

Cookies

We use cookies to ensure that the website functions properly. By selecting the "Accept" option, you agree to the use of all cookies in accordance with the Information for the use of cookies on the site.