August will be a dynamic month for #ICGB

August will be a dynamic month for #ICGB! Field teams are already setting up the stage for the most technically complex element in the entire IGB project – the crossing under the Studen Kladenets Dam.

The underwater section of the #pipeline has the impressive total length of 1 420 m. The drilling process will be implemented though the method of horizontal directional drilling (HDD) by a trusted contractor – the French company Horizontal Drilling International.

The entire process is expected to take a total of 152 days (97 days for site preparation and 63 for drilling activities) and estimated 72 hours of non-stop work for the final phase, when the entire welded and coated section of the pipeline will be pulled under the dam in one go. Work is underway and the crossing will be completed within the planned timeline.

The #IGB project is on track and all construction activities show steady progress during the summer months. You can see some of the achieved milestones in the latest video of the #interconnector Greece – Bulgaria.

Έργο IGB

Ο Διασυνδετήριος Αγωγός Φυσικού Αερίου Ελλάδας-Βουλγαρίας συγχρηματοδοτείται από το Ταμείο Ανάκαμψης του
Προγράμματος Ενέργειας της Ευρωπαικής Ένωσης.

Η αποκλειστική ευθύνη αυτής της δημοσίευσης ανήκει στον συγγραφέα.
Η Ευρωπαϊκή Ένωση δεν ευθύνεται για οποιαδήποτε χρήση των πληροφοριών που εμπεριέχονται σε αυτήν.

Co-financed by the Europen Union, Europen Energy Programme for Recovery  European Regional Development Fund Operational Program Innovation and Competitiveness

Cookies

We use cookies to ensure that the website functions properly. By selecting the "Accept" option, you agree to the use of all cookies in accordance with the Information for the use of cookies on the site.