Over 70 km of line pipes for the interconnector Greece-Bulgaria have been delivered
Over 70 km of line pipes intended for the construction of the Greece-Bulgaria gas interconnector have already been delivered on the territory of the two countries, with active work underway for clearing the route and stringing. The pipe stringing on Bulgarian territory reached 7 km. As of the beginning of May, line pipe welding activities have also been progressing. Currently, 50 manual welding procedures have been completed. Automatic welding is expected to start soon as well. The non-destructive testing of the welded connections has already begun. About 50 km of the land along the route of the IGB project has been cleared, with 35 km on the territory of Bulgaria, and the rest - on the territory of Greece.