Skip to main content

ICGB reached an agreement with the Greece-Bulgaria gas pipeline EPC contractor avoiding future litigation issues

The independent transmission operator ICGB reached an agreement with the EPC contractor for the Greece-Bulgaria gas interconnector construction, within the framework of which the indexation of the value of part of the construction and installation activities under the project was granted, and due penalties (delay liquidated damages) in favor of ICGB for delays in the construction of the pipeline as of 01.01.2022 were accepted.

In the framework of a lengthy negotiation process between the two parties and with the support of the Ministry of Energy of the Republic of Bulgaria, an agreement was reached to set off the full amount due by the EPC Contractor Liquidated Damages for delay from the total value of a counterclaim for indexation due to the inflation of some of the accepted and completed after 30.06.2021 construction and installation activities on the project.

According to the methodology adopted by the Bulgarian Council of Ministers in September 2022 regarding cost indexations of public procurement contracts because of inflation, contractors under contracts for construction awarded under public procurement procedures have the right to claim cost indexation due to increased prices of basic goods and materials forming the final cost of the construction contracts.

The contractor for the engineering, procurement, and construction (EPC) contract of the IGB pipeline presented the right to claim indexation of the contract under the provisions of the Public Procurement Act. In turn, the transmission operator ICGB, which is responsible for the operation of the facility, will deduct the full amount of due Liquidated Damages from the EPC contractor. In addition, the construction company will withdraw all pending claims for additional costs.

The agreement reached ensures that the accrued penalties are collected in favor of ICGB, prevents future disputes and possible arbitration proceedings, and lays a solid foundation for the conclusion of the contractual commitments by both parties without significant costs, resources, and contractual complications. It also saves resources for both parties, avoiding potential litigation risks, and allows them to focus on their core activities.

ICGB highly appreciates the agreement reached, which directly reflects the interests of the company. Withholding of penalties imposed on the EPC contractor, the agreed indexation is significantly below the real inflation for the period, and avoiding future disputes is entirely in favor of the transmission system operator. Despite the indexation, ICGB remains for its scale one of the cheapest energy projects implemented in the region. The total price per kilometer, including the cost of all above-ground installations – two gas metering stations, seven block valve stations, and a dispatching center – remains in the order of 1.3 million euros.

The agreement was reached thanks to the exceptional technical and legal preparation of the team engaged by the Bulgarian side on all pending issues, as well as the transparent and constructive approach in defending the company's position.

The agreement between the two parties will become effective only upon approval by ICGB’s shareholders.

IGB Project

Gas Interconnector Greece-Bulgaria is co-financed by the European Union's
European Energy Programme for Recovery programme.

The sole responsibility of this publication lies with the author.
The European Union is not responsible for any use that may be made of the information contained therein.

Co-financed by the Europen Union, Europen Energy Programme for Recovery  European Regional Development Fund Operational Program Innovation and Competitiveness

Cookies

We use cookies to ensure that the website functions properly. By selecting the "Accept" option, you agree to the use of all cookies in accordance with the Information for the use of cookies on the site.