ICGB invites five candidates for the second phase of the restricted procedure for design, procurement and construction of the gas interconnector Greece – Bulgaria

The project company announces serious progress in one of the key tenders for the IGB project; international and Bulgarian companies continue in the procedure

Yesterday – 13.02.2019 – the project company ICGB AD sent invitations to the candidates who qualified after pre-selection phase in the procedure for design, procurement and construction (EPC) of the gas interconnector Greece – Bulgaria.

The selection of a contractor is carried out through a restrictive procedure in two phases as per the Public Procurement Act - pre-selection, followed by review, evaluation and ranking of offers.

The first phase of the procedure is completed with the entry into force of the decision for pre-selection and the project company proceeded to sending the invitations to the candidates for the real competition.

As a result of applying the requirements for participation and the selection criteria, the candidates qualified for second phase are as follows:

  • DZZD "IGB-2018" with members: Bonatti S.p.A. (Italy), GLAVBOLGARSTROY INTERNATIONAL (Bulgaria), GP Group AD (Bulgaria);
  • Consortium MAX STREICHER – TERNA with members: Max Streicher (Italy) and Terna (Greece);
  • Consortium Spiecapag Trace IGB 2018 with members: Spiecapag (France) and Trace Group Hold AD (Bulgaria);
  • J&P AVAX S.A (Greece);
  • Joint Venture CPP-AKTOR with members: China Petroleum Pipeline Engineering Co. Ltd. (China) and Joint Construction Company AKTOR (AKTOR AD) (Bulgaria).

 “The successful finalization of the first phase of the procedure for selection of constructor is a serious progress on one of the most important tenders for the IGB project. All companies proceeding in the procedure have extensive experience and we are certain that they have the capacity to successfully carry out the project”, announced ICGB’s Executive Officers Teodora Georgieva and Konstantinos Karayannakos. According to them, the active international presence in the first phase of the procedure is a sign for serious competition, which will guarantee the high quality of work when completing the project for the gas interconnector with Greece.

Most candidates qualified for phase two are major international companies participating in consortiums with Italian, French, Chinese, Greek and Bulgarian companies. Only the Greek company J&P AVAX S.A. participates on its own.

The project company notes that according to the initially announced requirements of the documentation for the public procurement only 5 participants were to be shortlisted for second phase. This number has been achieved by ICGB through implementation of the selection criteria. The rest of the candidates did not fully meet the selection criteria and therefore the Contracting Entity did not invite them to the next stage of the procedure.

The deadline for submission of offers for the second phase of the tender is 35 days after receiving the invitation, meaning that it’s expected for all participants to submit their proposals by the 3rd week of March. According to the tender’s schedule, ICGB intends to finalize the technical assessment in a month after receiving the offers and plans to announce the Contractor by the end of April.

The project company thanks all participants for their interest and notes that it’s pleased with the very good level of competition achieved.

For more information:
Vladislava Tsekova
ICGB AD
Tel.: +359 2 926 38 62
Mobile: + 359 88 653 99 09

Date 14/02/2019

IGB Project

Gas Interconnector Greece-Bulgaria is co-financed by the European Union's
European Energy Programme for Recovery programme.

The sole responsibility of this publication lies with the author.
The European Union is not responsible for any use that may be made of the information contained therein.

Co-financed by the Europen Union, Europen Energy Programme for Recovery  European Regional Development Fund Operational Program Innovation and Competitiveness

Cookies

We use cookies to ensure that the website functions properly. By selecting the "Accept" option, you agree to the use of all cookies in accordance with the Information for the use of cookies on the site.